Important Notice To Pluris Wedgefield Customers

Late on the evening of August 21, 2026, a severe lightning strike caused damage to the water treatment facility, to include computers, SCADA, PLC’s, and communication equipment resulting in low water pressure for customers for approximately three hours. The SCADA system is purposely designed and programmed for an extreme event such as this to enter a fail-safe mode. The fail-safe mode ensures continuing operation of critical systems such as pumps and disinfection equipment. At no time did the system pressure drop below the Florida Department of Environmental Protection (“FDEP”) requirement of 20 psi. Our field crew immediately implemented emergency procedures and worked diligently to restore water pressure to affected customers as quickly as possible.

In addition, a 4-inch water main break occurred on Majestic Street, resulting in a temporary loss of water service to the 36 connections located along the street. Once the repair was completed, a precautionary Boil Water Advisory was issued, and affected addresses received the precautionary boil water notices by door tags. Our field crew followed established emergency procedures to restore water service and ensure that the appropriate precautionary boil water notices were provided to all affected customers.

Field operations staff were immediately deployed to the water treatment facility and the water main line break. The FDEP was noticed and updated through the events. Field operation staff assessed the lightning strike damages at the water treatment plant as well as repairing the watermain line, which was concluded at approximately 2 AM ET. Per FDEP requirements, bacterial water samples for laboratory testing were obtained and pending results expected later today (Tuesday August 25th) the precautionary boil water notice to the 36 residents should be cleared for the residents. The notice remains in effect until the laboratory provides the results and Pluris notifies the affected residents.

Our Customer Care number, 888-758-7471, is answered after hours by a service that was actively receiving calls throughout the low-pressure event. Due to the high volume of calls received, customers may have experienced a wait time. However, all calls were answered and promptly dispatched to our field crew, and customers were provided with available information regarding the emergency.

Please note that correspondence sent to our Customer Care email address, [email protected], is monitored during regular business hours and will be addressed by our representatives on the next business day.

We appreciate our customers’ patience and understanding as our field crews worked diligently to address these incidents and restore water service as quickly and safely as possible.

Pluris Alabama, LLC is constructing a new Drinking Water Facility to Provide Water to more Rural Alabama Residents

October 2016

Pluris Alabama, LLC is midway through construction of a new drinking water facility in a rural area of Northern Alabama. The new facility will complement the first facility constructed and in operation since 2012. The first facility serves approximately 6,000 residents and with completion of the new facility, Pluris expects to serve up to an additional comparable number of residents.

Pluris Alabama manager and long-time Alabama native Tony Cosby says, “There continues to be a real need for additional water resources in rural Alabama and Pluris is once again responding to the need with this facility.”

As with the existing drinking water facility, the new state of the art facility draws water from a well with an initial capability of up to one million gallons per day. Onsite storage (above photos) will allow for water storage of nearly one million gallons. This feature will allow Pluris to better manage daily demands by customers.

In addition to the onsite facility, Pluris is installing approximately five miles of water distribution pipelines to provide additional service to existing customers as well as new customers.

For more information readers are encouraged to reach Tony Cosby, Regional Manager for Pluris in Alabama. Tony can be reached at [email protected] or at his office in Alabama at (256) 710-9657.